Notice
서브이미지5
DAEDONG HEAVY INDUSTRY developments news
List | Previous | Next
 

POSCO Gwangyang No.3 Pickling Line

Writer DAEDONG | Date 2007-01-31 11:51 | Clicks 3,617

 

POSCO completed construction of No.3 Pickling & Oiling Line(POL) at Gwangyang Works on Jan. 19, 2007.which is expected to produce 0.8 million tons of high strength interior steel plate for automobile per year.

No.3 POL, which started test operation of some facilities of it in last Dec., sharply reduced cost especially in construction investment by reusing the facilities abandoned and suspended.

 

DAEDONG supplied the Central Processing Facilities of No.3 POL Line by the consortium with VAI CLECIM and awarded from POSCO for the tstanding contribution of timely delivery and early stabilization.

 

DAEDONG’s supplied facilities are as below;

 

  1) Entry Looper Car

  2) Entry Looper Arm

  3) Outboard Bearing

  4) Tension Reel & Mandrel

  5) Flying Shear

  6) Belt Wrapper

  7) Steering Roll Ass'y

  8) Dryer

  9) Pickling & Rinsing Line / Tank, Roll Ass'y, Fume Fan.

 10) Pickling Tank Roll Changing Car

 11) Pickling Tank Moving Frame

 12) Pickling Tank Moving Arm

 13) Skin Pass Mill (Reuse)

 14) Skin Pass Mill Gear Reducer

 
List | Previous | Next
 
TODAY 0 TOTAL 10
No Subject Writer Date Clicks
10 Visit of insepctor from SIEMENS VAI DAEDONG 11-1014:06 4349
9 Visit of POSCO Support Group DAEDONG 11-0911:06 4004
8 POSCO Gwangyang No.3 Pickling Line DAEDONG 01-3111:51 3618
7 Certification of INNO-BIZ DAEDONG 11-2411:49 2202
6 Exhibit “Guide Roller” AISTech 2006 DAEDONG 06-0211:43 2259
12last